ALBANY, N.Y., July 15 (TodayViralUSA) – New York has become the first U.S. state to pause permitting for large new data centers. Lawyers and energy analysts say the move will be closely watched as other states struggle with the power and water demands of the artificial intelligence boom.
Gov. Kathy Hochul signed Executive Order No. 62 on Tuesday. It takes effect immediately and suspends discretionary permits, approvals and licenses from the state Department of Environmental Conservation for building or expanding data centers of 50 megawatts or more. The governor has described it as a one-year pause.
What the order covers
According to analyses by the law firms Davis Polk and Harter Secrest & Emery, the moratorium generally does not apply to applications the department deemed complete before July 14, and it does not affect approvals at the local level. Facilities used primarily for manufacturing, research, education or medical care are exempt. The research exemption explicitly covers quantum computing and biomedical work, and the education exemption covers the state-backed Empire AI consortium.
The pause will remain in place until the Department of Public Service completes a generic environmental impact statement. That review is to examine energy demand, water use and quality, air quality, noise, and disproportionate effects on disadvantaged communities, and it will include public comment and hearings.
Grid pressure behind the decision
The order cites unprecedented demand. Nearly 12 gigawatts of data center load requests are pending in the state grid operator’s interconnection queue, and more than 8 gigawatts of that entered in 2025 alone. Hochul has said the cost of serving new data center load should not be shifted onto existing utility customers. She has also said she will seek legislation to repeal sales tax exemptions for data centers.
The order directs regulators to consider a New York Grid Acceleration Fund, which could require data center developers to make upfront contributions to grid infrastructure, fund an insurance pool, help procure new clean energy supply and take part in demand-response programs. A data center interconnection working group is to be formed within 60 days. Empire State Development is to draft a community investment framework to guide local negotiations over jobs, labor commitments and other benefits.
Executive action instead of legislation
The order follows a stronger legislative proposal. In June, state lawmakers passed the Responsible Data Center Development Act, which would impose a one-year moratorium on state permits for data centers with peak demand of 20 megawatts or more and require new electricity and water rate classes for large facilities. Harter Secrest & Emery noted that the bill had not yet been delivered to the governor, and her position on it was unclear.
Legal analysts note that the executive order is narrower than the bill. It uses a higher size threshold, includes broader exemptions, and leaves local approvals untouched. For developers, the immediate practical effect is uncertainty. Projects that had not reached a complete application by the cutoff now face an open-ended wait tied to the environmental review.
A model for other states?
Energy policy experts say New York’s approach, which pairs a temporary pause with work on rate design, grid financing and community benefit standards, offers a template that other states facing rapid load growth may study. Critics of moratoriums counter that pauses risk pushing investment and jobs to neighboring states without solving the underlying supply problem.
How New York handles the review, and whether it can produce durable rules within the promised year, is likely to influence how other legislatures respond to the data center build-out.
Sources & Credits
- Davis Polk: https://www.davispolk.com/insights/client-update/new-york-state-enacts-data-center-moratorium
- Harter Secrest & Emery: https://hselaw.com/news-and-information/legalcurrents/data-center-development-in-new-york-faces-immediate-pause-under-executive-order-62/
- AP News: https://apnews.com/article/new-york-data-centers-moratorium-ai-c1e05b74208a6c570eec7c658ac8f187